As a pioneer of the utility scale renewable power plant in Cambodia, SchneiTec Group has expanded rapidly to be one of leading renewable energy developers in the region. As a proof of that, we have invested and owned more 240 MW of solar PV power plants throughout the Kingdom, thereby supplying sustainable and clean energy more than 23 TWh every year to the national grid. Current portfolio of the company in Energy business consists mainly of renewable energy such as solar, Energy infrastructure such as transmission lines, and traditional source of energy such as HFO.
SchneiTec aims to expand into more renewable energy sources. Commencing from serving as the independent consultant and qualified expert for hydro power plants, SchneiTec Group has so far been looking deeper into hydro power plant sector, via developing a feasibility study that could eventually investing and owning the power plant in the near-distance future.
And is keen to work along-side competent authorities to fully develop Cambodia energy sector to achieve the 3 goals of the RGC.
Solar Projects
Project Name | Location | Output Capacity |
Solar Farm | Bavet City, Svay Rieng | 10 MW |
Solar Farm | Kampong Speu | 80 MW |
Solar Farm | Kampong Chnang | 60 MW |
Solar Farm | Pursat | 60 MW |
Solar Farm | Pursat | 30 MW |
Solar Farm | Takmao | 1.5 MW |
Off-grid solar home system | Police Maritimes Border Defend of Koh Thmey, Preah Sihanouk Province | 1 KW |
3 sets with backup time 30 minutes | Peace Palace | UPS 200kVA |
1 set with backup time 15 minutes | Ministry of Economic and Finance | UPS 200kVA |
Solar Farm | Kampong Chnang | 100 MW |
BESS Solar Farm | Kampong Chnang | 60 MW |
BESS Solar Farm | Pursat | 150 MW |
BESS Solar Farm | Kampong Chnang | 40 MW |
BESS Solar Farm | Pursat | 20 MW |
Firm Output Solar Farm | Pursat | 10 MW |
BESS Solar Farm | Svay Rieng | 60 MW |
Transmission Lines
High Voltage Lines:
- 500 kV Phnom Penh – Cambodia/Laos Border (300km)
- 500 kV Battambang – Cambodia/Laos Border (107km)
- 230 kV Tabong – Ratanakiri
Distribution Lines:
- 115 kV Siem Reap – Oddor Meanchey
23.4 km Line & 6km - Underground Line in Sihanouk Ville
Substations:
- 115/22 kV Oddor Meanchey Substation
- 230/22 kV Bekchan Substation
- 115/22 kV Sihanouk Ville 2 & 3 GIS Substations
HFO
SchneiTec has entered into 5 years O&M Technical Advisory Services Agreement with EDC for EDC C2 35MW Power Plant which focusing on a whole Operation & Maintenance of the Plant. SchneiTec has entered into Spare Parts Solution Agreement for both Scheduled and Unscheduled spare part with EDC for EDC C7 400MW HFO/LNG Power Plant which is the combination of following 2 power plants. SchneiTec will use their resource to assist EDC in term of spare part supply and management
List of Power Plant O&M:
- The COD of 23MW HFO Power Plant in SHV (15 May 2022)
- 400MW heavy fuel oil Power Plant, Kandal Province
- 35MW heavy fuel oil Power Plant, Kandal Province
Benefits of SchneiTec Energy Infrastructure
One-Stop Shop for Energy Solutions
A comprehensive suite of services encompassing all aspects of energy project development and management, from engineering and construction to operation and maintenance.
Local Expertise & Experience
We leverages our team of local engineers and construction personnel to deliver projects effectively. Our understanding of local regulations and experience working in Cambodia contributes to successful project execution and minimizes potential risks.
Focus on Efficiency & Uptime
We prioritizes efficiency and uptime in its projects. This is evident in our meticulous maintenance of solar farms and strategic use of local personnel for continuous monitoring.
Our Company under Energy Infrastructure Business
SchneiTec logo is more than just a symbol; it's a visual representation of our core values and unwavering commitment to Cambodia's sustainable future.